Commercial Window Installation — Cherry Picker Access
Project Overview
An office building in Nottingham was having a run of outdated single-glazed windows replaced with modern double-glazed units to improve comfort and reduce heating costs. With the windows spread across an upper floor and no balcony access, a cherry picker was used to reach each opening from outside.
The Work
Our glazing team worked window by window from the cherry picker, minimising internal disruption:
- Positioned a cherry picker to give safe external access to each window opening
- Removed the existing single-glazed window units from each frame
- Installed new double-glazed units into the existing openings, checking for square and level
- Sealed all frame perimeters with weatherproof sealant to prevent draughts and water ingress
- Fitted new trims and beading to match the building's existing external appearance
- Cleaned all new glazing on completion of each window
Results
The office building now benefits from improved comfort and reduced energy loss through its windows:
- A full run of upgraded double-glazed windows across the affected elevation
- Improved thermal comfort and reduced draughts reported by building occupants
- No internal scaffold or access equipment required inside the office
- Completed in 5 working days using external cherry picker access only